October 2007
|
initial planning meeting |
| October 2007 |
visit other university recreation centers |
| November 2007 |
determine scope of facility (size, location, cost) |
| January 2008 |
marketing throughout campus community |
| March 2008 |
student referendum |
| August 2008 |
receive funding for project |
| February 2009 |
design phase completed |
| May 2009 |
project in bid and awarded |
|
July 27, 2009
|
groundbreaking
|
|
Sept. 24, 2010
|
construction completed
|
|
October 2010
|
CSU Student Recreation Center GRAND OPENING
|
|